Shares of NHPC Ltd. are in focus after the state-owned hydropower company signed a Memorandum of Agreement (MoA) with the Government of Arunachal Pradesh for the development of the 3,097 MW Etalin Hydroelectric Project.
The project will be built on the Dri and Tangon rivers in the Dibang Basin and represents one of the largest hydropower projects under development in the country.
NHPC had a market capitalization of Rs. 75,087 crore, with the stock trading around Rs. 75. Its 52-week range stood between Rs. 71.62 and Rs. 89.75, while the trailing P/E ratio was about 20 times.
Project details
The agreement was signed on June 16, 2026.
The Etalin project is a run-of-river hydropower project and will be implemented under the Build, Own, Operate and Transfer (BOOT) model.
Key features include:
- Capacity of 3,097 MW
- Location on the Dri and Tangon rivers
- Situated in the Dibang Basin of Arunachal Pradesh
- Lease period of 40 years from the Commercial Operation Date (COD)
Scope of the agreement
Under the MoA, the Arunachal Pradesh government has allowed NHPC to undertake:
- Preliminary investigations for the Pre-Feasibility Report (PFR)
- Detailed studies for the Detailed Project Report (DPR)
- Financing activities
- Project development
- Commissioning
- Operation and maintenance
The project is being developed under the Arunachal Pradesh Hydro Power Policy, 2008.
According to the company, the project is expected to support renewable power generation and contribute to infrastructure and economic development in the state.
NHPC’s operations
NHPC is India’s largest hydropower producer in terms of installed capacity.
As of May 2026, the company operated:
- 31 power stations
- Total installed capacity of 9,333 MW
This includes:
- 8,771 MW of hydropower
- 562 MW of renewable energy capacity
The company accounts for 16.57 percent of India’s installed hydro capacity.
Financial performance
For FY26, NHPC reported:
- Revenue from operations of Rs. 11,615 crore
- Revenue of Rs. 10,380 crore in FY25
Net profit attributable to shareholders rose to Rs. 3,766 crore, compared with Rs. 3,007 crore in FY25.
The company reported an EBITDA margin of 59 percent.
NHPC has set a consolidated capital expenditure target of Rs. 15,000 crore for FY27.
Project pipeline
With the addition of the Etalin project, NHPC’s development pipeline includes:
- 9,204 MW under construction
- 10,263 MW awaiting clearances
The company has yet to receive investment approval for the projects awaiting regulatory permissions.
TL;DR:
NHPC has signed an MoA with the Arunachal Pradesh government to develop the 3,097 MW Etalin Hydroelectric Project. The project will be executed under the BOOT model with a 40-year lease period and adds to NHPC’s expanding hydro power pipeline.
AI summary:
- NHPC signed an MoA for the 3,097 MW Etalin Hydroelectric Project.
- The project is located on the Dri and Tangon rivers in Arunachal Pradesh.
- It will be developed under the BOOT model with a 40-year lease.
- NHPC reported FY26 net profit of Rs. 3,766 crore.
- The company has over 19 GW of projects under construction or awaiting clearances.