Pune–Shirur Elevated Corridor Project: April 2025 Update
The Pune–Shirur Elevated Corridor marks a significant infrastructure upgrade, aimed at easing congestion and enhancing connectivity between Pune and Shirur, with future plans to extend it to Chhatrapati Sambhajinagar.
Current Status (April 2025)
The tendering process for the project is in its final stages, with bids opened on April 1, 2025, and allocation expected by April or May.
- Financial closure is projected between June and July 2025, setting the stage for construction commencement.
Construction work is anticipated to begin shortly after financial closure, likely by June or July 2025.
- Authorities have streamlined processes to ensure swift transition from bidding to on-ground activity.
Land acquisition requirements are minimal, as the corridor will primarily use the existing Pune–Shirur highway alignment.
- This strategic approach minimizes displacement and expedites project rollout.
The project timeline targets completion within four years from the actual start of construction.
- Officials are optimistic about meeting these deadlines given the advanced pre-construction preparations.
Project Highlights
The elevated corridor will greatly enhance connectivity and is expected to deliver several key benefits:
- Reduced travel time and alleviated congestion on the Pune–Nagar Road, benefiting areas like Yerawada, Kharadi, Wagholi, Lonikand, Shikrapur, and Shirur.
- Seamless linkage to the Hindu Hrudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg via Shendra MIDC, significantly boosting regional access and trade.
The corridor also carries economic significance:
- Recognized in the Maharashtra Budget 2025–26, the project is positioned as a catalyst for economic activity and logistics efficiency.
- It will drive faster, safer travel for both freight and passengers, enhancing business competitiveness.
Implementation will follow a PPP (Public-Private Partnership) model, ensuring no direct fiscal burden on the state government.
- The elevated highway will feature multiple entry and exit points, serving important urban centers such as Ahmednagar and Chhatrapati Sambhajinagar.
Recent Developments
The Maharashtra State Cabinet approved the project in 2024, officially transferring its execution from NHAI to MSIDC.
- This move streamlined administrative processes and accelerated tendering timelines.
The project has successfully cleared major pre-bid and regulatory hurdles, placing it firmly on track for mid-2025 groundbreaking.
- Local commuters and stakeholders have welcomed these developments, anticipating major improvements in mobility and economic prospects.
Summary Table
Phase | Start Point | End Point | Length | Status (April 2025) | Completion Target |
---|---|---|---|---|---|
Phase 1 | Kharadi Junction | Shirur Bypass | 53.4 km | Tendering/Financial Close | 4 years post-start |
Phase 2 | Shirur Bypass | Sambhajinagar | 192.5 km | DPR stage | – |
The Pune–Shirur Elevated Corridor is primed to become a major transportation artery, with construction likely to begin by mid-2025.
- With financial closure, land acquisition, and government clearances almost complete, the project promises to transform regional connectivity, ease congestion, and boost economic growth between Pune, Shirur, and beyond.